Previous Projects
2002
Summit Resources Limited
(Medicine River) Engineering design and construction management of gas well production facilities and pipeline.
EOTT Canada Ltd.
(Edmonton Area) Regulatory compliance management and technical support for midstream oil treating and terminalling, and water disposal operation.
Murphy Oil Company Ltd.
(Provost) Design and construction management of 12,000 BPD waterflood plant and 32 km. injection pipeline system.
(Wilson Creek) Preliminary production development and facility design for sour oil/gas well tie-in.
2001
Purcell Energy Ltd.
(Fireweed, B.C.) Engineering design and construction management of gas well production facilities and pipeline.
(Pine Creek, AB) Project management for dual gas well tie-in.
(Joarcam) Pipeline leak detection and line repair management.
(Minton, Sk) Development of specifications and regulatory conditions for oil marketer tank farm expansion.
Summit Resources Limited
(Neptune) Engineering design, procurement and construction management of 2 oilfield satellites, 3 oil flowlines and battery free-water knock-out.
(Lougheed, Sk) Engineering design, procurement and construction management of oilfield satellite, oilwell tie-in and water disposal pump.
(Benson, Sk) Engineering design, procurement and construction management of oilfield satellite and well tie-in.
Murphy Oil Company Ltd.
(Chicken Ck., B.C.) Preliminary design management for critically-sensitive gas well tie-in in B.C. foothills.
(Niton) Project management for installation of 200 HP field booster compressor station.
(Gilby) Project management for installation of 1200 HP plant compressor; study and implementation of noise reduction equipment.
(Cranberry) Project management for installation of 500 HP field booster compressor, re-configuration of field production facilities.
(Lindbergh) Design and fabrication management of vent gas conservation equipment.
2000
Infiniti Resources International Ltd.
(Boundary Lake) Oilwell pump evaluation, reservoir commingling application and waterflood evaluation.
Murphy Oil Company Ltd.
(Boundary Lake) Design and construction management of production facilities and pipelines to tie-in 2 gas wells.
Belmont Energy Ltd.
(Grand Forks) Oilwell optimization.
Response Energy Corporation
(Pembina) Well program development and management of rig operations for 8 well abandonment project.
Penn West Petroleum Ltd.
Preliminary design for alternate sour gas pipeline system tie-in to Minnihik-Buck Lake Plant.
Palliser Energy Ltd.
(Provost) Preparation of annual waterflood progress report.
Touchstone Energy Ltd.
(Carrot Creek) Oil flowline and water injection pipeline system design.
Tiger Calcium Services Inc.
Brine source well development appraisal, evaluation of fuel gas reserve acquisition.
Vermillion Resources Ltd.
(West Pembina) Project management of 25 MMcfd gas plant re-construction following fire, liaison with insurance adjusters.
Purcell Energy Ltd.
(Minton) Design and construction management of oil field satellite upgrade with installation of separation, 150 HP pump and flare system.
Torex Resources Ltd.
(Neptune, Sk) Engineering design, procurement and construction management for 4 oil well tie-ins
(Alderson) Design and construction management for installation of 2 wellsite booster compressors.
1998/99
Westhill Resources Limited
(Barrhead) Petroleum engineering development to initiate production from a Banff oil/gas reservoir.
Design and construction management of central battery facilities and pipeline system for 5 MMscfd / 600 BOPD.
On-going operations management.
(Chestermere) Operations support for sour oil & gas field located within 5 km. of City of Calgary limits.
Brigdon Resources Inc.
(Red Willow) Project engineering for the design and installation of 10 km. pipeline to tie-in 5 sweet gas wells.
Purcell Energy Ltd.
Interim operations management of 1000 BOE/d junior public company.
(Rapdan) Design and construction management of oil battery and flowline system upgrade.
Iron Horse Compression (1996) Ltd.
On going application support for oil production optimization equipment - local and international.
1997
Anderson Exploration
(Piping/Vessel Specifications) Co-ordination and development of updated corporate specifications.
(Stoddart) Design and project co-ordination of sour B.C. battery upgrade.
(Cecil North) - Design and project management for tie-in of two horizontal oilwells.
Rosza Petroleum Ltd.
(Carmangay) Oil battery upgrade design and as-built drawing preparation.
(Lomond) Oil battery modification preliminary design.
Anadime Processing & Disposal Inc.
(Hays) Disposal well re-completion and EUB approval for Class 1b disposal.
(Project development) Fox Ck and Cold Lake area waste disposal wells.
1996
Canadian 88 Energy Corp.
(Olds Unit) Engineering design for sour gas (25% H2S) compressor station expansion to 40 MMscfd.
Gulf Canada Resources Ltd.
(Strachan) Facility co-ordination for sour gas well tie-ins and compressor station expansions.
Cimarron Petroleum Ltd.
(Gilby) Process engineering and regulatory approvals for gas plant expansion to 20 MMscfd.
(Lathom) Process engineering and regulatory approvals for 10 MMscfd gas plant development. Design and regulatory approvals for 15 km pipeline system.
Anadime Processing & Disposal Inc.
(Provost) Disposal well completion design and EUB approval for Class 1b disposal.
(Project Development) Morinville and Elk Point area waste disposal plants.
1995
Talisman Energy Inc.
(Lac La Biche District) Production and development engineering for 8 area gas fields - 42 MMscfd production.
Project management for compression/dehydration plant expansion to 7.6 MMscfd.
Management of 12 shallow gas well workover and re-completion program.
Canadian 88 Energy Corp.
(Olds Unit) Engineering contractor for design and management of critical sour gas (25% H2S) wellsite production facilities and pipeline installations - 7 projects during 1995.
Capital Cost $3,000,000
Encal Energy Ltd.
(Worsley) Design and construction management of water disposal facility for oil production battery and fibreglass pipeline system tie-in to disposal well.
Anadime Corporation
Regulatory application and testing program preparation for Class 1b waste disposal well.
1994
Talisman Energy Inc.
(Lac La Biche District) Production / development engineering and facilities design for 6 area gas fields - 20 MMscfd production.
Summit Resources Limited
Completion design and programming of two Sask. oilwells, two B.C. gas wells and nine Alberta oil/gas wells.
Encal Energy Ltd.
(Athabasca) Production facility design, procurement and construction management for 1994 Central District Gas Development Project (10 well program).
(Worsley) Design and construction management of oil production system (6 wells) including test satellite and group pipeline tie-in to central treating facility.
(Worsley) EPCM contractor for Worsley 12-22 Gas Processing Plant (10 MMscfd raw inlet capacity).
Project cost / duration - $1.7 million / 7 months.
Canadian 88 Energy Corp.
(Crossfield) Engineering design and management for critical sour (25% H2S) gas well pipeline and wellsite production facilities.
Harbour Petroleum Ltd.
(Red Willow) Alberta Environment pipeline application for creek crossing.
Newport Petroleum Corporation
(Worsley) Design / construction management for oil satellite and flowline system for six sour oil wells.
1993
Norwich Resources Canada Ltd.
(Princess) Evaluation and workover program development for 30 well shallow gas field, resulting in 25% production increase.
Encal Energy Ltd.
(Whitecourt) Gas well pipeline and production facilities design.
Summit Resources Limited
(Craigmyle/Delia) Detailed well evaluation of fifty shut-in area wells for workover/re-completion potential or abandonment.
Geoservices Ltd. (France)
(Pakistan) Project Technical Manager for engineering design and on-site construction of a 30 MMscfd sour gas plant, located 85 km southwest of Islamabad in the Ratana gas field.
Project duration - 4 months.
Talisman Energy Inc.
(Lac La Biche) Project engineer for 8 well shallow gas drilling, completion and pipeline project.
Project cost - $1,200,000
Cimarron Petroleum Ltd.
Preparation and submission of ERCB applications - 2 Compressor Stations, 2 Gas Plant modifications.
1988 - 1992
Project / production engineering and field supervision in oil and gas fields located throughout Alberta for the following companies:
Allied Hydrocarbons Inc.
Ascentex Resources Ltd.
Chinook Management
Columbia Gas Development of Canada Ltd.
Erehwon Exploration Ltd.
Excel Energy Inc.
Harrington - Bibler Inc.
J.M. Huber Corporation
Koch Exploration Canada, Ltd.
McGinnis Industries Ltd.
Newalta Corporation
Poco Petroleums Ltd.
Reed Resources Ltd.
Seguro Resources Ltd.
Skyline Natural Resources Ltd.
Summit Exploration Ltd.
Truax Resources Corporation
Upside Development Corporation
Valley (1987) Partnership No. 1
|